Construction Update​

Jinnah height 1 Construction going very fast. every month 2 slabs are completed. In Sha Allah project will be complete in 2024.

11/11/2022
Pouring Of Concrete 13th floor Slab's
20/10/2022
Pouring Of Concrete 12th floor columns
10/10/2022
Pouring Of Concrete 12th Slab
09/09/2022
Pouring Of Concrete 11th floor Columns
29/08/2022
Pouring Of Concrete 10th floor Slab's
30/07/2022
Pouring Of Concrete 11th floor columns

19/06/2022
Pouring Of Concrete 9th floor columns

13/06/2022
Pouring Of Concrete 8th floor Slab

25/05/2022
Pouring Of Concrete 7th floor Slab

14/04/2022
Pouring Of contract 6th floor slab

20/04/2022
Pouring Of Concrete 7th floor columns

30/04/20222
Pouring Of Concrete 8th floor columns

31/03/2022
Pouring Of contract 6th floor Columns

08/03/2022
Pouring Of Concrete 5th floor columns

01/03/2022
Pouring Of Concrete 4th floor slab

15/02/2022
Pouring Of Concrete 4th floor columns

25/01/2022
Pouring Of Concrete 3rd floor columns

22/12/2021
Pouring Of Concrete 2nd Floor

29/11/2021
1st floor columns

19/11/2021
Pouring Of Concrete Ground Floor Roof Filling

06/11/2021
Pouring Of Concrete Ground Floor Columns

01/11/2021
Pouring Of Concrete Ground Floor Columns Beams

12/10/2021
1st Phase Of Ground Floor Pouring

10/6/2021
Opening Ceremony